Shutdown Excellence

Case description

One shut-down day can be very expensive for a production unit. In the current case, the company consisting of 9 production areas had each year 326 shutdown days.

Method

Workshops were facilitated to get a full overview of the current status and roles & responsibilities during a shutdown​. A playbook was made with execution templates, risk assessments, clear timelines, calendar, and standard roles & responsibilities to ensure a strong and efficient shutdown organization.

Result

30 % reduction of shutdown days
70% Reduction of shut-down related deviations
An increased utilization of resources in the shutdown phase.

News

Two companies becoming one…

We are pleased to finally share the news that Kuatro Group ApS …

Scroll to Top

Menu

We service the largest Life Science companies on many different levels on a daily basis. The key aspects and the common feature of our consultants are our high professional level we possess.

Menu

We service the largest Life Science companies on many different levels on a daily basis. The key aspects and the common feature of our consultants are our high professional level we possess.

We use cookies to give you the best experience. By using our site, you accept the use of cookies.